The project covers the repair of severely damaged Jetty.
Engineering, Procurement, Installation and Commissioning Of New Service Berth at Ras Laffan
Engineering, Procurement, Installation and Commissioning of New Service Berth at Ras Laffan.
The scope covers the construction of Service Berth complete with 530 m long precast concrete blockwork quay wall, fill roads, drainage, duct bank crossings.
Marine Terminal Inside Benghazi Harbour and Pipelines Between Harbour and Ras El Mungar Terminal
Detailed field engineering , design, procurement and supply of equipment and materials,
transport, construction, installation, testing and commissioning of marine tanker unloading/loading Facilities inside Benghazi New Harbour and laying required pipeline.
Extension Of Hereke Port Hereke
The scope of work includes the construction of a 198 m long and 60 m wide steel pipe pier.
Additional Extension Of Hereke
The scope of work includes the construction of an additional 145 m long and consisted of Quarry with steel piles and 133+12=145 m length, 49.50m wide steel pipe pier.
A New Port and Fishery Harbour at Wilayat Sohar
The scope covers the construction of 1070 m concrete blockwork quaywall (for a dredged depth of 16m), 850 m piled rear crane beam, 30 m transition quaywall.
Rota Cement Factory Quay Piling Works
The project covers a 126.7 m long, 15.75 m wide berth construction on 144 nos 55×55 cm precast concrete piles and a 5,52 m long 5.06 m wide platform constructed on 4 nos of 55 x 55 cm precast concrete piles.
Ras Gas Onshore Expansion Project, Design and Construction Of Lng Berth No. 3 and Flares
The project comprised of the construction of a concrete block loading platform and two breasting, eight mooring dolphine structure. Other than 3 flares, the structure was constructured offshore.
Construction Of Quaywalls (phase 2) for the New Port and Fishery Harbour at Wilayat Sohar
The project covers 810 m of quaywall with 132.000 m3 of P/C Blocks, 21.000 m3 of cast-in-place concrete, 310.000 m3 of stone works and 1.600.000 m3 of reclamation works. The project is expected to be completed in 18 months.
Construction Of Bulk Liquid Berth C1 for the New Port and Fishery Harbour at Wilayat Sohar
The Contract comprises the construction of the 451 meter long Bulk Liquid Berth C1 for the New Industrial Port and Fishery Harbor at Sohar including, driving of 222 nos steel piles with diameters 1016mm, 1220 mm, 1520mm, 1370mm with lengths of 35 metres.