Artell Koytür BUYAKA Projects

STFA has received the Temporary Completion Certificate for the 1st and 2 nd Phase of the Artell Koytür BUYAKA Projects Building Pit Construction.

For the shoring works of The Artell Koytür Çekmeköy Residence’s Phase 1 and Phase 2 Foundation Pits, STFA has received The Temporary Completion Certificate on 1 March 2007. The contract was signed on 15 June 2006 between STFA Temel Pile Construction Co. And Artell Koytür Tourism Construction Industry and Trade Co.

The project scope also covered the soil improvement works of the foundations for 3 towers with 28 storeys. Design process continues in guidance of the accomplished soil investigations.

Hubara-Sahmah & Sahmah Pipeline

Contract award for Hubara-Sahmah & Sahmah-KP114 Pipeline Project in Oman

STFA, in joint venture with FERNAS, has been awarded by Petroleum Development Oman a contract worth 40,500,000 US Dollars for Hubara-Sahmah & Sahmah-KP114 Pipeline.

The project covers laying of pipes 32” 102km between Sahmah and KP114 and also laying of pipes 28” 114km between Sahmah-KP114 as an EPC Contractor.

Asia and Europa with a Water Conveyance Tunnel

After linking two continents first with a bridge, next with an energy transmission line, STFA is now linking two continents, Asia and Europa with a Water Conveyance Tunnel

OJSC MOSMETROSTROY-ALKE-STFA J.V. has signed a contract on 28.November.2006 with State Hydraulic Works of Turkey for Bosphorus Tunnel Crossing project.

The aim of the project is to supply water for European side of Istanbul from Big Melen River by a tunnel constructed beneath Bosphorus.

The project having a value of 127,527,563 US Dollars comprises of :

Bosphorus Crossing Tunnel with diameter 5820 mm and length 5550m at

135m below sea level.

90m cut and cover tunnel (between Ortaçeşme and Bosphorus)

Beykoz shaft with inner diameter 8m with depth 145m – upto the base of

Bosphorus Tunnel

Access galleries with length 221m at European side of Bosphorus

Tunnel Crossing

Steel lining works of all the tunnels having 4m inner diameter

Electrical and mechanical works

7 Project in Qatar

STFA proceeds with Construction of New Temporary Berth No: 7 Project in Qatar

STFA Marine Construction Company has signed a contract with Qatar Petroleum Company for Construction of New Temporary Berth No: 7.

The 17,823,322 US Dollars project has a construction period of 7 months and covers the construction of a berthing structure having 140 m length  with alll mooring equipments and related items.

Küçüksu & Küçükçekmece

STFA awarded Temporary Completion Certificate for Küçüksu Wastewater Pretreatment Plant & Sea Outfall Project and Küçükçekmece Sea Outfall Improvement Works

Küçüksu Wastewater Pretreatment Plant & Sea Outfall Project and Küçükçekmece Sea Outfall Improvement Works which has been awarded by Istanbul Water and Sewerage Administration on 10.May.2001 has been completed and Temporary Completion Certificate  been awarded on 15.May.2006.

The project covered the construction of 1035m long Küçüksu Tunnel, Küçüksu Marine Outfall and  Küçükçekmece Sea Outfall Improvement works.

The Küçüksu Marine Outfall covers the construction of 1,361m long (Onshore Section) Ø 2200mm Steel Pipes and 363m long (offshore section) Ø 2200mm Steel Pipes.

The project value is 21 Million US Dollars.

Sirte-Misurata

STFA awarded 400 kV 392 km Sirte-Misurata Overhead Transmission Line Project worth 110 M USD in Libya

STFA has been awarded 400 kV 392 km Sirte – Misurata Overhead Transmission Line Project in Libya.
The contract value is 110 million US Dollars and the contract is expected to be signed by August.

Jufra Housing Project

STFA awarded Integrated Infrastructure Works of Jufra Housing Project in Houn Area, Libya

STFA has signed a contract with General Company for Construction of Administrative Centers (CAC) of Libya for Integrated Infrastructure Works of Jufra Housing Project in Houn Area.

The project covers the construction of roads, electrical network, street lightening, telecommunication network, rainwater sewerage system and has a value of  21,303,217 US Dollars.

System of Sohar Industrial Area

STFA granted Temporary Completion Certificate for Seawater Intake and Return System of Sohar Industrial Area in Oman

Temporary Completion Certificate of Seawater Intake and Return System of Sohar Industrial Area project has been received on 10.May.2006. The contract was signed on 20.November.2002 between the Ministry of National Economy of Oman and STFA – BAHWAN Consortium.

The project realised in Sohar Industrial Area on EPC basis covered the construction of Seawater Intake and Outfall works. The project consists of a seawater intake designed for a maximum flow rate of 334,000 m3/h and an outfall designed for a maximum flow rate of 325,000 m3/h. The total value of the project is 52,081,780 US Dollars.

Sohar Aluminum Smelter Project

STFA awarded Bored Piling Works of Sohar Aluminum Smelter Project in Oman

STFA Temel Pile Construction Company has been awarded Bored Piling Works of Sohar Aluminum Smelter Project in Oman on 10.May.2006. The client is Sohar Aluminum Smelter Company LLC and EPC Contractor is Bechtel & Co. LLC.

The project covers the construction of bored piles with diameters varying  from 600 mm to 1000 mm and lengths from 27.5 m to 35 m. The pile loading tests are within the scope of the contract. The value of the project is 6,149,750 US Dollars.

Iskenderun Iron & Steel Works Company

STFA awarded contract for the Soil Investigation and Drilling Works of Iskenderun Iron and Steel Works Company

STFA Temel Investigation and Drilling Company has been awarded a contract for  the Soil Investigatio and Drilling Works on 01.May.2006  by Iskenderun Iron and Steel Works Company. The project is  within the content of Isdemir Modernization Investments-2 Project .

The contract includes the engineering, procurement, fabrication, installation, and precommissioning  works. The duration of the contract is 90 days and the value is  378,574 YTL + KDV.