The project covers the 393 numbers of towers, 152 km wire stringing and commissioning of the transmission line.
132/33/11 Kv Süleymania Substation Erection, Test and Commissioning
132/33/11 KV Süleymania Substation Erection, Test And Commissioning – IRAQ
Nassiriya Thermo Power Plant
Nassiriya Thermo Power Plant – IRAQ
51nos 33/11 Kv 2×31.5 Mva Substations Test and Putting into Service
Erection Works Of 51nos 33/11 KV 2×31.5 Mva Substations Test And Putting Into Service – IRAQ
400 Kv, 348 Km Altinkaya-kayabaşi, Kemerköy-yatağan, Karakaya-keban Transmission Lines
The project covers the 873 numbers of towers, 8,575 tons tower fabrication, civil works, 6,124 tons erection and 348 km transmission line.
400 Kv, Karakaya-keban Transmission Line
The project covers the 688 tons tower fabrication, civil works, and 688 tons erection of the transmission line.
154 Kv, 245 Km Elbistan-pinarbaşi -gölbaşi and Kalecik-esenboğa Transmission Lines
The project covers the fabrication and erection of 755 numbers of towers, 245 km wire stringing and commissioning of the transmission line.
400 Kv, 220 Km Atatürk-gaziantep-erzin Transmission Line
The project covers the fabrication and erection of 5,795 tons tower, civil works, 221 km wire stringing and commissioning of the transmission line.
132/33/11kv Zakho Substation
132/33/11kV Zakho Substation – IRAQ
380 Kv, 221 Km Atatürk-gaziantep-erzin Transmission Line
The project covers the fabrication and erection of 546 numbers of towers, 221 km wire stringing and commissioning of the transmission line.