Final Acceptance Letter Has Been Received For Khasab-Tibat Road Project

Final acceptance letter has been received on 07.06.2021 for the “Improvement of Existing Khasab to Tibat Coastal Road” Project, which was undertaken as STFA İnşaat by the contract signed on 17.06.2014 with the Ministry of Transport and Communications.

The project consists of the construction of a single carriageway road, slope stabilization, rock fill, and shore protection works.

Substantial Completion Certificate Has Been Received For “Improvement Of Existing Khasab Tibat Coastal Road” Project In Oman

Improvement of Existing Khasab Tibat Coastal Road Project which was undertaken by the contract signed on 18.09.2014 completed on 31.12.2019 and Substantial Completion Certificate has been received on 12.02.2020.

Within the scope of the project, consisting of 6 sections, a total of 27 km, 238.000 m2 slope stabilization, 3.2 M m3 rock filling, 1.5 M m3 coastal protection filling and 45 culvert construction works have been completed.