FABRICATION YARD AREA
The fieldwork of the investigation included drilling of total 6 nos boreholes 2 nos testpit 8 nos piezocone,

ONSHORE GAS TERMINAL AREA
The fieldwork of the Investigation included drilling of total 20 nos boreholes, 5 nos testpits execution of 20 nos piezocone tests, 2 nosof siesmic downhole test and 3 nos soil resistivity survey

ONSHORE PIPELINE
The fieldwork of the investigation included drilling of total 41 nos boreholes, 22 nod testpits and execution of 58 nos soil resistivity measurements at boreholes and testpit location.