The project covers a total of 617 boreholes and 193 testpits at the Central & Eastern Branch and Abu Aisha Storage Reeservoirs in Libya.
Gas Transmission Pipeline to Coastal Network Geotecnical Investigations
67 boreholes with max. Depths up to 40m, 31 nos of testpits were executed along the pipeline route, PRMS and 103A compressor station sites.
Tripoli Tee to Bir Tirfas Conveyance Line and Water Storage Tanks Geotechnical Factual Report
The purpose of the project was to design and install a water conveyance pipeline system, in order to serve the coastal area agricultural projects, to the west and south west of Tripoli.
Eni Gas B.v., Libyan Branch, Western Libya Gas Project, Supply Base and Tugboat Harbour Geotechnical
The objective of this investigation was to determine the subsoil conditions at the site, so as, to provide information related to the evaluation of the subsurface conditions. Onshore investigation consisted total of 29 boreholes with a maximum depth of 35m.
Great Man Made River Project, Phase 3, Al Kufra Wellfield to Tazerbo Conveyance Pipeline & Phase 3 Pump Stations
Al Kufra to Tazerbo Conveyance Pipeline conveys water pumped from Al Kufra wells in the south -eastern region of Libya to the coastal strip to supply agricultural, municipal and industrial water needs.
Petronas Carigali Turkmenistan Block 1 Feed Study Geotechnical Investigations
The project covers the geotechnical investigations for the 50 km long onshore pipeline, navigational channel, onshore gas terminal and fabrication yard.
Gmmr Project Phase4 Ghademes-zwara Water System Geotechnical Investigations
The scope of work covers the geotechnical investigatins along the 622 km long proposed pipeline route.
Al Jaghboub-tobruk Line Water Conveyance Project Geotechnicl Investigations
The scope of work includes the geotechnical investigations along the 300 km long water supply project.
400 Kv, 500+75 Km Tripoli – Sirte Transmission Line System
The project covers the 500 km+75 km(%15) km 400 kV, SC OH Energy Transmission Line From between Tripoli-Sirte. Energy Transmission between Tripoli-Sirte via an OHTL 400 kV Single Circuit triple conductors.
Const. Of 200 Kv 327 Km Double Circuit Double Phase Overhead Energy Transmission Line
The project covers the construction of 327 km+49 km(%15) km 220 Kv, Double Circuit, OH Energy Transmission Line from GMMRA-2 SS to GMMRA-1 to SEPHA 18TH km.