“Sharq” Launching Ceremony Held In Doha Metro, Gold Line Underground Project

Works are ongoing with full pace in the design and build contract “Gold Line Underground” which was signed with Qatar Rail on April 23, 2014.

The first of six Herrenknecht Tunnel Boring Machines (TBM 1) that will excavate one of the tunnels of the project, has been launched successfully as planned, with a ceremony held at the Airport City North Station on February 22, 2015. “Sharq” name was given to TBM 1.

Sharq will start excavation at the Airport City North Station, and follow a course through National Museum/Al Sharq and Doha Souq Station, reaching to the Msheireb Station about 4 km ahead. Once the tunnel excavation is completed, it will be dismantled and removed from the tunnel through the previous station to the surface.

Final Acceptance Letter Has Been Received For Epic For Gabbro Berth Expansion (Pack. 1) At Mesaieed Port

Final Acceptance Letter has been received on February 2, 2015 for the “Engineering, Procurement, Installation and Commissioning for Gabbro Berth Expansion (Package1) at Mesaieed Port” Project, undertaken as STFA-JDN Consortium according to the agreement signed with Qatar Petroleum in on May 1, 2008 in Qatar,

The project includes 400m of quay wall construction (bedding, leveling, scour protection, underwater block placement), block fabrication, preloading of the Quay Wall, backfilling, quay furniture Installation (fenders, bollards, rings, ladders, etc.), cranes rails piles and beams, 4 nos. of STS gantry cranes, electrical and mechanical works, substation building, lighting and cabling, infrastructure works.

Provisional Acceptance Letter Has Been Received For Tupras New Jetty Project

Provisional acceptance letter has been received on 31.01.2015 for Izmit Refinery Zone B –Rehabilitation of Quay and Construction of New Jetty Project, which was undertaken as STFA-Körfez Deniz JV by the contract signed on 04.07.2013 with Tüpraş.

Project covers the 780 m long jetty with steel piles, rehabilitation of 571 m long quay with steel piles, removal of existing jetty, Mechanical Works including 2.144 ton piperack installation and 43km process piping, electrical and instrumentation works.

STFA Won Qatar Doha Metro “Gold Line” Tender

STFA, Within a Consortium of Five, Competed Against World’s Biggest Companies and Won Qatar Doha Metro “Gold Line” Tender for $4.4 billion

STFA, Turkey’s leading construction company with important and prestigious construction projects domestically and abroad, have won the “Gold Line” tender, the largest line within the Qatar Doha Metro, as part of a consortium of five, named ALYSJ.

The Gold Line tender, one of the investments being made in preparation for 2022 World Cup, is the biggest project in Qatar for this purpose with a cost of $4.4 billion.

With the signing ceremony held on April 23, 2014, STFA with its partners achieved the biggest tender ever won by Turkish contractors abroad.

Construction projects proceed without slowing down in the Gulf country Qatar, which will host the 2022 World Cup. Many companies from Turkey and around the world have put in for the projects in Qatar, which include Metros, underground stations, railroads, stadiums, shopping malls, hotels, highways, bridges, immersed tunnels and reservoirs. About 700 companies showed interest in one of the most important of these projects, the Doha Metro tender, and 70 joint ventures made up of 290 of these companies submitted competency files. The employer lowered the number of joint ventures first to 32, then to 18 and invited these joint ventures for the tenders. The $4.4 billion-worth Gold Line packet of the Doha Metro, made up of four main lines, was signed by STFA and its partners.

This project reinforces STFA’s presence in Qatar and the Middle East as well as the strategic positioning as the leading international constructor.

Groundbreaking Ceremony Held For “Small Boat Harbours” Project İn Kuwait

The Groundbreaking Ceremony of STFA’s Monumental Project “Small Boat Harbours” Took Place with the Participation of The President of Republic of Turkey Mr. Abdullah Gul and Kuwait Minister of Oil and Minister of State for National Assembly Affairs Dr. Ali Omair

 

Foundation stone for STFA’s first project “Small Boat Harbours” in Kuwait had been laid with the participation of The President of Republic of Turkey Mr. Abdullah Gül and Kuwait Minister of Oil and Minister of State for National Assembly Affairs Dr. Ali Omair on April 2nd, Wednesday. The ceremony was attended by government officials from Kuwait, corporate representatives of the involved enterprises, Turkish and Gulf region press and guests.

 

STFA, the Pioneer Turkish contracting company in the international arena, representing the knowledge and expertise of Turkish engineering and reflecting a 36 years of engagement and experience in the region was proud to announce the Small Boat Harbours Project, valued at 490 million USD, which will be completed within 38 months.

Region’s Face will change!

Under the patronage of Kuwait Oil Company (KOC), “Small Boat Harbours” project consists of capacity extension of the Al Ahmedi Harbour and a new construction of a service harbour at Abu Halifa. The project is aimed to be completed within 38 months.

 

Kuwait Oil Company (KOC) is a subsidiary of the Kuwait Petroleum Corporation (KPC), a government owned holding company. KOC’s responsibilities involve the exploration, drilling and production of oil and gas within the State of Kuwait. The Company is also involved in the storage of crude oil and delivery to tankers for export. STFA, also cooperates with the local companies Canar and Imco for the infrastructure, construction of the buildings and electromechanical aspects of the project.

 

The project is split between two main locations, being the North and South projects, 7 km. apart from each other. The scope of the project consists of dredging of harbor basin, construction of piers, quay walls, pontoons, ship lift systems containing marine works, superstructure buildings and landscaping, electrical and mechanic works and ICT (Marine and Building Management Systems and Telecommunication Systems).

 

Long breakwater, in total 4km, will be constructed to protect the harbors by using quarried rock material of 2.5 million tons and 26,000 special protective concrete units called Accropode II.

 

The Quay wall, 2.5 km. length in total will be constructed by using 12,000 concrete block units in the sea and the quay walls will accommodate all the needs of future marine fleet of KOC. In order to serve the bigger marine assets of KOC, both harbors will be dredged down -7 meters CD, and the landfill attained during this dredging will be used as for the filling materials in the North and South harbours. There will also be a state of the art maintenance shipyard inclusive of a ship lift, in a capacity to serve 3 vessels at the same time.

 

Chairman of the Board of Directors Mr. Alp Taşkent, in his speech, said: “We are proud to add Kuwait’s “Small Boat Harbours” project to our GCC portfolio, in a region where we can reflect back 36 years of engagement and experience. At the same time, we also bear the responsibility of adding an important milestone in the cooperation of our countries.”

Khan Academy Türkçe And Turkcell Akademi Cooperation

Khan Academy Türkçe and Turkcell Akademi Cooperation

 

On a mission to provide a free world-class education to anyone, anywhere, Khan Academy videos are now available in Turkcell Academy, as a result of the collaboration with Turkcell.

 

Turkcell has recently launched its education platform, Turkcell Academy. As a result of the cooperation between Turkcell Academy and Scientific and Technical Publications Translation Foundation, an STFA foundation, Khan Academy became the major content provider and the lessons in Turkish are now being streamed on Turkcell Academy. Aiming to provide a free world-class education to anyone, anywhere, Khan Academy Turkish lessons are now expected to reach many more users with Turkcell’s support.

 

Khan Academy’s content is completely free of charge and available to anyone.

 

With over two thousand educational videos translated into Turkish so far, Khan Academy provides  a personalized education experience at one’s own learning pace. Thanks to the cooperation between Turkcell Academy and Khan Academy Turkce, these educational opportunities will be made even easier to reach.

Two New Projects İn Oman

We signed a Contract for the Musannah Fishing Port Project &We received an invitation for Musannah Treatment Plant Project , We signed a Contract for the Musannah Fishing Port Project

We signed a contract for the “Musannah Fishing Port” project of Oman Ministry for Agriculture and Fisheries on December 5, 2013.The contract was signed on behalf of the Ministry for Agriculture and Fisheries by the minister, H.E. Dr. Fuad bin Jaafar al Sajwani, and on behalf of STFA by the member of our Board of Directors, Mr. Nur Taşkent.

 

The project is in the town of Musannah, 160 kilometers from Muscat. The project includes the construction of a wharf of 150 meters, and breakwaters of 1627 meters as well as dredging works of up to 5 meters in depth.

 

 

We received an invitation for Musannah Treatment Plant Project

We received an invitation from the Directorate General of Wastewater of Oman Ministry of Regional Municipalities and Water Resources for the “Musannah Sewer System and Treatment Facility” project. We’d placed a bid for the project on February 18, 2013. The employer informed us with a letter on December 15, 2013 that we won the tender and invited us to sign the contract.

 

Included in the project are HDPE and UPVC sewer pipelines of 65 km in length and 200 to 500 mm in diameter and construction of one pumping plant and water supply station, as well as design and construction of one wastewater treatment plant (oxidation-type treatment plant).

One Of The Caissons Have Been Floated

In İzmit Bay Crossing Project, One of the Caissons Have Been Floated

An important phase of the Izmit Bay Crossing Project has been successfully completed. In a ceremony attended by the Minister of Transport Binali Yıldırım, the Director General of Highways, and senior managements of the project’s main contractors NOMAYG, IHI and STFA, one of the caissons upon which the abutments will be constructed has been floated (27.09.2013).

 

One of the caissons have been floated to the Temporary Supply Dock on the coast of Kaytazdere, 11 km from the drydock on Yalova’s Hersek Cape. The other caisson is expected to be floated in the upcoming days.

 

The caisson floating ceremony received great interest from the Highways senior officers to authorities from surrounding counties, from the main contractor’s senior executives to the press and the local population. An important milestone for the project was thus completed with great enthusiasm and success. In the next phase, work will commence at the sea.

Groundbreaking Ceremony Held At Erbil, Iraq

Groundbreaking Ceremony Held for “Erbil Drinking Water Improvement and Erbil & Duhok Network” Project in Iraq

The groundbreaking ceremony for the “Erbil Drinking Water Improvement and Erbil & Duhok Network” project, undertaken as an STFA-FERNAS-KALYON Joint Venture in Iraq, was held. The ceremony took place at the 50,000 m3 capacity water reservoir being built by the joint venture in Erbil, on September 19, 2013 and was attended by the Prime Minister of Kurdistan Regional Government Nechervan Barzani, the Turkish Consul General in Erbil Mehmet Akif İnam, Commercial Attaché Sayer Erbil, Senior Management from STFA, Fernas and Kalyon.